Drivers, transit riders and businesses along Ninth Line should keep planning around construction for at least another year, as the road widening between Eglinton Avenue and Derry Road is still expected to reach substantial completion by the end of 2027.
The latest project update, posted October 22 on Ward 10 Coun. Sue McFadden's website, says another intersection closure was required at Platinum Drive and Ninth Line from November 2 to November 7 to allow construction of the storm sewer system and an oil-grit separator structure.
During that closure, Eglinton Avenue and Ridgeway Drive served as alternate routes, with detour signs posted on site. The update says the work was coordinated with nearby businesses and Sherwood High School, with a Paid Duty Officer assigned and an additional flagperson stationed at the entrance of the Autospa. Construction notices were hand delivered to affected businesses, including a gas station and a Tim Hortons, and portable message signs warned the public in advance.
What the finished road will look like
Construction on the major capital project officially began in June, with a June 8 groundbreaking attended by officials from the Ontario Ministry of Infrastructure, MPP Sheref Sabawy and City of Mississauga staff, according to McFadden's update.
The design largely follows an environmental assessment approved in 2021, according to the City of Mississauga. Once complete, Ninth Line will carry two travel lanes in each direction, separated by raised medians or centre left-turn lanes, with a protected cycle track and a distinct sidewalk on both sides.
New traffic signals are planned for Skyview Street/Mahoney Gate, Tacc Drive, McDowell Drive and Beacham Street, and a new MiWay transit route is expected to service the full length of Ninth Line. The Ontario government has provided $10 million in grant funding for the project.
Transit and traffic impacts
The speed limit in the work area has been reduced to 40 km/h to protect road users and construction workers. Recent work has concentrated between Eglinton Avenue and Tacc Drive, including full-depth asphalt removal, grading between Eglinton and Candlelight Drive, installation of 18 catch basins from Henrietta Way to Lacman Trail, and temporary hydro poles at signalled intersections.
MiWay riders face ongoing changes. Routes 49 and 49A McDowell have some stops temporarily out of use along Ninth Line, with buses detouring via Raftsman Cove. Stop #4902 on northbound Ninth Line at Lacman Trail is closed, directing riders to stop #4903 on McDowell Drive at Swordsman Drive, about 275 metres northeast. Stops 3570, 3501 and 3417 on Erin Centre Boulevard, served by Route 9, are also affected.
Tree removal part of the plan
Mature trees have been removed along the corridor in recent weeks to make room for the wider road, sidewalk and east-side cycle track. According to the update, those trees were located within the right-of-way and their removal was always part of the widening plan. Hydro pole relocation has also been underway.
Earlier this year, Platinum Drive was closed at Ninth Line for about three weeks starting August 31, and similar closures were scheduled at the Stardust, Skyview and Candlelight intersections. The City says residents and commuters should expect dust, noise, and road and lane closures throughout the roughly 18-month build, and are encouraged to plan for delays or take alternate routes where possible.